Project Name | The Interlocking Blocks Project in Ningbo Beilun Meishan Bonded Port | ||
Project Location | Ningbo, China | Engineering Costs | 1.25 million yuan |
Start time | October, 2015 | Completion time | December, 2015 |
Company | Name | ||
Owner | Ningbo Port Group Co., Ltd. | ||
Design | CCCC Third Harbor Consultants Co., Ltd. | ||
Supervisory | Ningbo Port Harbor Engineering Co., Ltd. | ||
Project Overview | |||
The total area of the interlocking block section in the engineering yard is 17,950 square meters. Strength above C50, thickness of 8 centimeters, 7,000 square meters of 12 centimeters thick. |
Ningbo Xiaolang Construction Engineering Co., Ltd.
Ningbo Tianyuan Cement Products Co., Ltd.
Yuehu Ginza, Nanzhan East Road, Haishu District, Ningbo City
+86 574 8698 8331